| Section 6 |
| Installation of the lower roofing membrane layer |
100% |
✅ |
| Installation of the upper roofing membrane layer |
25% |
🟠 |
| Installation of porcelain stoneware facade tiles (courtyard side) |
90% |
🟢 |
| Installation of metal facade framework (courtyard side) |
90% |
🟢 |
| Installation of insulation on the stairwell |
90% |
🟢 |
| Reinforcement mesh over insulation on the stairwell |
90% |
🟢 |
| Section 7 |
| Installation of heating risers on floors 2–14 |
100% |
✅ |
| Floor screed installation on floors 10–14 |
100% |
✅ |
| Wall plastering on floors 5–14 |
100% |
✅ |
| Section 9 |
| Construction of pylons and walls on floors 17–20 |
100% |
✅ |
| Installation of floor slabs on floors 17–19 |
100% |
✅ |
| Exterior walls on floors 5–6 |
100% |
✅ |
| Interior walls on floor 5 |
50% |
🟠 |
| Exterior and interior walls on floor 7 |
70% |
🟢 |
| Parking |
| Installation of ventilation ducts on level -4 |
100% |
✅ |