Details Completion Status
Section 6
Installation of the lower roofing membrane layer 100%
Installation of the upper roofing membrane layer 25% 🟠
Installation of porcelain stoneware facade tiles (courtyard side) 90% 🟢
Installation of metal facade framework (courtyard side) 90% 🟢
Installation of insulation on the stairwell 90% 🟢
Reinforcement mesh over insulation on the stairwell 90% 🟢
Section 7
Installation of heating risers on floors 2–14 100%
Floor screed installation on floors 10–14 100%
Wall plastering on floors 5–14 100%
Section 9
Construction of pylons and walls on floors 17–20 100%
Installation of floor slabs on floors 17–19 100%
Exterior walls on floors 5–6 100%
Interior walls on floor 5 50% 🟠
Exterior and interior walls on floor 7 70% 🟢
Parking
Installation of ventilation ducts on level -4 100%
Share