Section 3

  • The process of building networks continues: power supply, water supply, heating, fire protection systems, commercial and household drain, outdoor engineering systems, elevator equipment;
  • The installation of fencing balconies, loggias and cold passages is finished;
  • The device of screed for loggias and cold transitions has begun;
  • Joining the roof has finished;
  • Installation of the facade elements of the 1st floor and the stained glass system continues;
  • Installation of brackets and porcelain stoneware of the ventilated facade continues;
  • Installation of the wet facade continues.

 

Section 5

  • The installation of the floor slab continues.

 

Parking

  • Pile chipping completed;
  • The installation of vertical elements continues.

More construction photos in our Gallery 📸