Section 3

  • The process of building networks continues: power supply, water supply, heating, fire protection systems, household drain, outdoor engineering systems, elevator equipment;
  • Installation of concealed installation doors has begun;
  • The process of installing cold screed, apartment and wheelchair loggias has been completed;
  • Installation of the facade elements of the 1st floor and the stained glass system continues;
  • Installation of the subsystem and insulation of the ventilated facade continues;
  • Installation of a wet facade continues;
  • Installation of floor tiles on 7 – 13 floors continues;
  • Warming of the ceiling with mineral wool on -1 floor proceeds.

 

Section 5

  • The installation of vertical elements continues;

 

Parking

  • Concreting the console of the fence;
  • The installation of the floor slab continues.

 