Section 3
- The process of building networks continues: power supply, water supply, heating, fire protection systems, household drain, outdoor engineering systems, elevator equipment;
- Installation of concealed installation doors has begun;
- The process of installing cold screed, apartment and wheelchair loggias has been completed;
- Installation of the facade elements of the 1st floor and the stained glass system continues;
- Installation of the subsystem and insulation of the ventilated facade continues;
- Installation of a wet facade continues;
- Installation of floor tiles on 7 – 13 floors continues;
- Warming of the ceiling with mineral wool on -1 floor proceeds.
Section 5
- The installation of vertical elements continues;
Parking
- Concreting the console of the fence;
- The installation of the floor slab continues.