Section 3

  • installation of facade elements
  • screed of common areas and apartments of 6-13 floors
  • plastering common areas -1, 13 floors
  • work has been done on the installation of the frame of stained glass systems on the 1st floor
  • work has been done on waterproofing and insulation of the external wall -1 floors
  • installation of porcelain stoneware and wet facade is being carried out
  • roofing work is being carried out
  • installation of elevator equipment is being carried out

 

Section 4

  • Pile field; concrete preparation

 

Section 5

  • monolithic work on the construction of vertical structures 2 level
  • work has been done on the installation of floor slab

 

More construction photos in our Gallery 📸