Section 3
- monolithic work on the construction of vertical and horizontal structures at the level of the 14th floor (terrace)
- brickwork of external and internal walls -3 -13 floors and roof
- installation of window blocks completed
- installation of facade elements
- screed of common areas and apartments of 2-5 floors
- plastering common areas 2-12 floors
Section 4
Pile field; concrete preparation
Section 5
- monolithic work on the construction of vertical structures