Section 3

  1. monolithic work on the construction of vertical and horizontal structures at the level of the 14th floor (terrace)
  2. brickwork of external and internal walls -3 -13 floors and roof
  3. installation of window blocks completed
  4. installation of facade elements
  5. screed of common areas and apartments of 2-5 floors
  6. plastering common areas 2-12 floors

 

Section 4
Pile field; concrete preparation

 

Section 5

  • monolithic work on the construction of vertical structures

 