Section 3

  1. The installation of external walls of ceramic blocks at the level of the 8th and 9th floors
  2. The device of the floor slab at the level of the 12th floor
  3. Concreting of vertical elements at the level of 12th floors
  4. Arrangement of flights of stairs from the 9th to the 10th floor
  5. Installation of ventilation units

 

Section 4

Pile field, soil development according to the project

Section 5

Soil development, concrete preparation of grills, backfill of grills

 